Pile testing (Pile Drive & Pull-Out), Samarkand 2 Solar 500 MW
Pile testing (Pile Drive & Pull-Out), Samarkand 2 Solar 500 MW · Client: OOO "JURU ENERGY CONSULTING"
Pile testing under two load types at the site of the «Pile drive and Pull-Out Test at 500MW PV Plant» as a part of the 500MW & 772 MWh Samarkand 2 Solar PV & BESS Independent Power Project, located in the Nurabad district, Samarkand region, Republic of Uzbekistan.
Project details
Field
Geology
Type of work
Pile testing (Pile Drive & Pull-Out), Samarkand 2 Solar 500 MW
Client
OOO "JURU ENERGY CONSULTING"
Service
Geophysical surveys
Similar projects
Engineering-geological survey of a power line (51 km), 500 MW solar plant (Sherabad)
Engineering-geological survey of a power line (51 km), 500 MW solar plant (Sherabad)
Client: China Machinery Engineering Corporation (CMEC), ООО «HEX Solar»
Drilling works (2000 m), Fergana region
Drilling works (2000 m), Fergana region
Client: OOO "HEJINHUA GROUP"
Geotechnical and geophysical works, «Bash and Jankeldy» (Bukhara region)
Geotechnical and geophysical works, «Bash and Jankeldy» (Bukhara region)
Client: FE (CHINA ENERGY INTL GROUP CAS) ООО
Geotechnical surveys, LNG peak-shaving facility (Syrdarya, Tashkent, Turakurgan)
Geotechnical surveys, LNG peak-shaving facility (Syrdarya, Tashkent, Turakurgan)
Client: SEPCOIII ELECTRIC POWER CONSTRUCTION CO., LTD.
Engineering-geological surveys, combined power plant 1500–1700 MW (Uchkizil, Termez)
Engineering-geological surveys, combined power plant 1500–1700 MW (Uchkizil, Termez)
Client: «SEPCOIII Electric Power Construction Co. LTD»
Geotechnical studies, Nukus WPP (Karakalpakstan)
Geotechnical studies, Nukus WPP (Karakalpakstan)
Client: Power China Huadong Engineering Corporation Limited SINOHYDRO TASHKENT LLS